5-5
8.
From the QTP menu bar, select I
NSERT
>C
HECKPOINT
> S
TANDARD
C
HECKPOINT
. The cursor becomes a pointed finger.
9.
Click on the words "I
NSERT
D
ONE
..." in the progress bar with the pointed finger.
10. In the O
BJECT
S
ELECTION
-C
HECKPOINT
P
ROPERTIES
window, click OK. The
C
HECKPOINT
P
ROPERTIES
window opens (
Figure 5-2
).
Figure 5-2
11. The property you want to use as a verification is the text I
NSERT
D
ONE
...Deselect all
other checkboxes and select the text property. I
NSERT
D
ONE
...should appear in the
C
ONSTANT
field as shown in
Figure 5-2
.
12. Click OK to close the C
HECKPOINT
P
ROPERTIES
window.
13. In the Flight Reservation application, click F
ILE
> N
EW
O
RDER
to set the end
condition of the test to match the conditions that existed when the test began.
14. Stop the test.
15. Save the test.