How would you estimate the amount of re-testing likely to be required?
Software Testing Exam from International Software Testing Qualifications Board (ISTQB)
(Continued from previous question...)
How would you estimate the amount of re-testing likely to be required?
How would you estimate the amount of re-testing likely to be required?
a) Metrics from previous similar projects
b) Discussions with the development team
c) Time allocated for regression testing
d) a & b
Answer: D