What is the purpose of test completion criteria in a test plan:

Software Testing Exam from International Software Testing Qualifications Board (ISTQB)


(Continued from previous question...)

What is the purpose of test completion criteria in a test plan:

What is the purpose of test completion criteria in a test plan:

a) to know when a specific test has finished its execution
b) to ensure that the test case specification is complete
c) to set the criteria used in generating test inputs
d) to know when test planning is complete
e) to plan when to stop testing

Answer: