Given the following sets of test management terms (v-z), and activity descriptions (1-5), which one of the following best pairs the two sets?v – test controlw – test monitoringx - test estimationy - incident managementz - configuration control
Software Testing Exam from International Software Testing Qualifications Board (ISTQB)
(Continued from previous question...)
Given the following sets of test management terms (v-z), and activity descriptions (1-5), which one of the following best pairs the two sets?v – test controlw – test monitoringx - test estimationy - incident managementz - configuration control
Given the following sets of test management terms (v-z), and activity descriptions (1-5), which one of the following best pairs the two sets?v – test controlw – test monitoringx - test estimationy - incident managementz - configuration control
1 - calculation of required test resources
2 - maintenance of record of test results
3 - re-allocation of resources when tests overrun
4 - report on deviation from test plan
5 - tracking of anomalous test results
a) v-3,w-2,x-1,y-5,z-4
b) v-2,w-5,x-1,y-4,z-3
c) v-3,w-4,x-1,y-5,z-2
d) v-2,w-1,x-4,y-3,z-5
Answer: C
(Continued on next question...)