According to the lecture, there are several risks of managing your project's schedule with a statistical reliability model. These include:

Software Testing Exam from International Software Testing Qualifications Board (ISTQB)


(Continued from previous question...)

According to the lecture, there are several risks of managing your project's schedule with a statistical reliability model. These include:

According to the lecture, there are several risks of managing your project's schedule with a statistical reliability model. These include:

A. Testers spend more energy early in the product trying to find bugs than preparingto do the rest of the project's work more efficiently
B. Managers might not realize that the testing effort is ineffective, late in the project,because they expect a low rate of bug finding, so the low rate achieved doesn'talarm them.
C. It can increase the end-of-project pressure on testers to not find bugs, or to notreport bugs.
D. All of the above

Answer: B