A project that is in the implementation phase is six weeks behind schedule. The delivery date for the product is four months away. The project is not allowed to slip the delivery date or compromise on the quality standards established for this product. Which of the following actions would bring this project back on schedule?

Software Testing Exam from International Software Testing Qualifications Board (ISTQB)


(Continued from previous question...)

A project that is in the implementation phase is six weeks behind schedule. The delivery date for the product is four months away. The project is not allowed to slip the delivery date or compromise on the quality standards established for this product. Which of the following actions would bring this project back on schedule?

A project that is in the implementation phase is six weeks behind schedule. The delivery date for the product is four months away. The project is not allowed to slip the delivery date or compromise on the quality standards established for this product. Which of the following actions would bring this project back on schedule?

A. Eliminate some of the requirements that have not yet been implemented.
B. Add more engineers to the project to make up for lost work.
C. Ask the current developers to work overtime until the lost work is recovered.
D. Hire more software quality assurance personnel.

Answer: