A project manager has been transferred to a major software development project that is in the implementation phase. The highest priority for this project manager should be to

Software Testing Exam from International Software Testing Qualifications Board (ISTQB)


(Continued from previous question...)

A project manager has been transferred to a major software development project that is in the implementation phase. The highest priority for this project manager should be to

A project manager has been transferred to a major software development project that is in the implementation phase. The highest priority for this project manager should be to

A. Establish a relationship with the customer

B. Learn the project objectives and the existing project plan

C. Modify the project’ s organizational structure to meet the manager’ s management style

D. Ensure that the project proceeds at its current pace


Answer: B